Nexans powers up Interxion’s London data centres

Palfreyman Power equipped  50,000ft2 of space in the Old Truman Brewery, East London with electrical and mechanical infrastructure including: climate control, fire detection, gas suppression, security & CCTV, leak detection, power, standby power, cabling and containment.

Power cables were installed under raised anti-static computer flooring and Nexans Lineax H07RN-F cable was selected to power the mission critical facilities including: five back up generators, tri-vector UPS systems, four 11kV/400V transformers, switchgear and intelligent PDUs.

Nexans worked closely with Harding Electrical to project manage the stock of pre-cut lengths to ensure the cable could be called off as and when required. One of the main challenges was delivering the product into central London on a timed delivery basis with limited space for offloading. Due to space limitations on site Nexans also collected the empty cable drums once the cable had been installed.

Interxion supports over 1,300 customers through 33 data centres across 11 countries, enabling these customers to securely deliver mission critical applications and content to end consumers, with excellent response time performance.

  • Show Comments (0)

Your email address will not be published. Required fields are marked *

comment *

  • name *

  • email *

  • website *

You May Also Like

Study concludes that STP cables are superior for 10 Gigabit Ethernet environments

Study concludes that STP cables are superior for 10 Gigabit Ethernet environments Results of ...

TalkTalk

Is Industrial Scale Fraud Being Perpetrated On UK TalkTalk Customers?

There is industrial scale fraud being perpetrated on UK customers of the British telecoms ...

Mapped out

Mapped out Siemon has launched the MapIT G2 Copper Interconnect System. This network management innovation ...

Share This